QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

BUNLOINN WIND FARM AND BESS

At FORT AUGUSTUS

SSEN Embedded Capacity Register, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2035
Status
Accepted to connect
Customer
Not stated
Site name
BUNLOINN WIND FARM AND BESS
Address
BUNLOINN, INVERGARRY, HIGHLAND, IV63 7YN
Grid reference
Easting 227912, northing 812485
Licence area
North of Scotland (SHEPD)
Grid supply point
FORT AUGUSTUS
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 71.6 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 5.5 MW registered
Registered capacity
71.6 MW
Change to maximum export capacity
71.6 MW
Change to maximum import capacity
5.5 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
5 Jun 2025
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
July 2025 edition

Change history

Tracked since the July 2025 edition, across 15 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at FORT AUGUSTUS

GSP view

4 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 172 MW: 51 MW connected, 121 MW accepted to connect.

  • MILLENNIUM EAST WIND FARMMILLENNIUM EAST WIND FARM, Wind, FORT AUGUSTUS GRID primaryAccepted49.9 MW
  • AUCHTERAW FARMFIELD AUCHTERAW LTD, Storage, FORT AUGUSTUS GRID primaryConnected47.405 MW
  • GLEN BUCK HYDROGREEN ENERGY TRADING LTD, Hydro and marine, FORT AUGUSTUS GRID primaryConnected1.943 MW
  • ALLT LADAIDH HYDROGREEN HIGHLAND ALLT LADAIDH (1148) LIMITED, Hydro and marine, FORT AUGUSTUS GRID primaryConnected1.283 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose