QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

New Hall Farm BESS

New Hall Farm BESS at Elland

Northern Powergrid Embedded Capacity Register 1MW and Over, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Customer
New Hall Farm BESS
Site name
New Hall Farm BESS
Address
New Hall Farm, Whitwell Green Lane, Elland, West Yorkshire, HX5 9PH
Grid reference
Easting 411811, northing 421044
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
Elland
Bulk supply point
New Hall Farm BESS
Primary substation
New Hall Farm BESS Direct
Connection voltage
132 kV
Technology group
Storage
Energy source 1
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 99.9 MW registered, storage 300 MWh, 3 hours of storage
Registered capacity
99.9 MW
Change to maximum export capacity
99.9 MW
Change to maximum import capacity
94.905 MW
Flexible connection
Yes
In a connection queue
Not published by Northern Powergrid
Date accepted
3 Dec 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Jan 2025
Tracked since
April 2026 edition

Change history

Tracked since the April 2026 edition, across 6 editions.

Another record at this location is on a separate page.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Elland

GSP view

22 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 531 MW: 155 MW connected, 376 MW accepted to connect.

  • Lowfields Way BESSLowfields Way BESS, Storage, Lowfields Way BESS Direct primaryAccepted100 MW
  • Elland 65 MW BESSElland 65 MW BESS, Storage, Elland BESS Direct primaryAccepted65 MW
  • Lowfields BESSLowfields BESS, Storage, Lowfields Buisness Park BESS Direct primaryConnected49.9 MW
  • Thornhill CCGTThornhill CCGT, Gas and other fossil, Thornhill Cogen Generation primaryConnected47.5 MW
  • Brighouse Power BESSBrighouse Power BESS, Storage, Brighouse Power BESS primaryAccepted40 MW
  • Mirfield BESSMirfield BESS, Storage, Mirfield BESS primaryAccepted40 MW
  • North Dean BESSNorth Dean BESS, Storage, Salterhebble primaryAccepted25 MW
  • Todmorden Moor Wind FarmTodmorden Moor Wind Farm, Wind, Todmorden Moor Windfarm primaryConnected19.999 MW

See all 22

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose