Blyth Offshore Windfarm Add

Blyth Offshore Windfarm, Bath Lane Meter at Blyth 66kV

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
28 Nov 2000
Status
Connected
Customer
Blyth Offshore Windfarm, Bath Lane Meter
Site name
Blyth Offshore Windfarm Add
Address
Blyth Offshore Windfarm Add, Blyth Offshore Windfarm, Blyth, Northumberland, NE24 3AT
Grid reference
Easting 431861, northing 581488
Licence area
North East (Northern Powergrid)
Grid supply point
Blyth 66kV
Bulk supply point
Blyth 66kV
Primary substation
Maddison Street
Connection voltage
11 kV
Technology group
Wind
Energy source 1
Wind, Offshore wind turbines: 3.8 MW registered
Registered capacity
3.8 MW
Maximum export capacity
3.8 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
Not stated
Target energisation date
Not published by Northern Powergrid
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
1574000181519
Import MPAN
Not stated
Last updated
10 Sep 2024
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Blyth 66kV

GSP view

24 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 602 MW: 140 MW connected, 462 MW accepted to connect.

  • West Sleek Burn BESSWest Sleekburn BESS, Storage, West Sleekburn BESS primaryAccepted70 MW
  • Broadway House FarmBroadway House, Solar, Broadway House PV primaryAccepted59.8 MW
  • Blyth Offshore WindfarmBlyth Offshore Wind Farm - Remaining Buildout, Wind, Blyth Offshore Windfarm primaryAccepted58.4 MW
  • Broadway House FarmBroadway House Farm PV, Solar, Broadway House Farm PV primaryAccepted50 MW
  • LOW HORTON FARMLow Horton BESS, Storage, Low Horton primaryAccepted44 MW
  • Burnt House FarmBurnt House 40MW Solar PV, Solar, Burnt House primaryAccepted42.24 MW
  • Blyth Offshore WindfarmBlyth Offshore Windfarm - Currently Installed, Wind, Blyth Offshore Windfarm primaryConnected41.5 MW
  • Burnt House FarmBURNT HOUSE FARM Additional BESS, Storage, Burnt House primaryAccepted40 MW

See all 24

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?