Barnsley Road PV

Barnsley Road PV at Elland

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Customer
Barnsley Road PV
Site name
Barnsley Road PV
Address
Barnsley Road, Flockton, Wakefield, West Yorkshire, WF4 4DN
Grid reference
Easting 422383, northing 415128
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
Elland
Bulk supply point
Thornhill 132kV
Primary substation
Mirfield
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 0.975 MW registered
Energy source 2
Wind, Onshore wind turbines: 0.08 MW registered
Registered capacity
1.055 MW
Change to maximum export capacity
1.055 MW
Change to maximum import capacity
2.138 MW
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
24 Feb 2026
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
12 Mar 2026
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Elland

GSP view

22 other sites at this grid supply point in the November 2026 edition, 1 of them at Mirfield, the same primary substation. In all, the sites here total 531 MW: 155 MW connected, 376 MW accepted to connect.

  • Lower Brighouse WTWLower Brighouse WTW, Gas and other fossil, Mirfield primaryConnected1.5 MW
  • Lowfields Way BESSLowfields Way BESS, Storage, Lowfields Way BESS Direct primaryAccepted100 MW
  • New Hall Farm BESSNew Hall Farm BESS, Storage, New Hall Farm BESS Direct primaryAccepted99.9 MW
  • Elland 65 MW BESSElland 65 MW BESS, Storage, Elland BESS Direct primaryAccepted65 MW
  • Lowfields BESSLowfields BESS, Storage, Lowfields Buisness Park BESS Direct primaryConnected49.9 MW
  • Thornhill CCGTThornhill CCGT, Gas and other fossil, Thornhill Cogen Generation primaryConnected47.5 MW
  • Brighouse Power BESSBrighouse Power BESS, Storage, Brighouse Power BESS primaryAccepted40 MW
  • Mirfield BESSMirfield BESS, Storage, Mirfield BESS primaryAccepted40 MW

See all 22

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?