ROANHEAD SOLAR FARM
NOVENTUM POWER LIMITED at HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUP
ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- Not stated
- Status
- Accepted to connect
- Customer
- NOVENTUM POWER LIMITED
- Site name
- ROANHEAD SOLAR FARM
- Address
- ROANHEAD SOLAR FARM, ROANHEAD FARM, BARROW IN FURNESS, CUMBRIA, LA14 4QL
- Grid reference
- Easting 321532, northing 476692
- Licence area
- North West England (ENWL)
- Grid supply point
- HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUP
- Bulk supply point
- ULVERSTON
- Primary substation
- ASKAM & DALTON
- Connection voltage
- 11 kV
- Technology group
- Solar
- Energy source 1
- SOLAR, PHOTOVOLTAIC: 10 MW registered
- Registered capacity
- 10 MW
- Maximum export capacity
- 0 MW
- Maximum import capacity
- 0 MW
- Change to maximum export capacity
- 10 MW
- Change to maximum import capacity
- 0.15 MW
- Flexible connection
- No
- In a connection queue
- No
- Date accepted
- 25 Jan 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by ENWL
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 13 Feb 2023
- Tracked since
- May 2026 edition
Change history
Tracked since the May 2026 edition, across 2 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUP
GSP view126 other sites at this grid supply point in the September 2026 edition, 5 of them at ASKAM & DALTON, the same primary substation. In all, the sites here total 2.8 GW: 0.8 GW connected, 2 GW accepted to connect.
- BENNETT BANK LANDFILL SITEINFINIS ENERGY SERVICES LIMITED, Bioenergy and waste, ASKAM & DALTON primaryConnected3.1 MW
- THORNTON WASTE TECHNOLOGY PARK, FLEETWOOD ROAD NORTHTHRIVE RENEWABLES (HAVERIGG II) LTD, Wind, ASKAM & DALTON primaryConnected1.25 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose