Renewco Power Ltd
Customer named in the DNOs’ registers
In SPEN’s September 2026 and ENWL’s October 2026 editions
The registers spell this customer’s name more than one way: “Renewco Power Ltd” (2 sites) and “RENEWCO POWER” (1 site).
Capacity by DNO
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 2 | 110 MW | – | 110 MW |
| Solar | 1 | 28 MW | – | 28 MW |
Each site is grouped by its first energy source, as the register names it.
Sites
Each site under this name in the DNOs’ latest editions, the largest first.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Site | DNO | Grid supply point | Technology | Status | MW |
|---|---|---|---|---|---|
| Fechan Generation Facility (Minsca extension) | SPEN | Chapelcross | Storage | Accepted to connect | 60 |
| Erkeksi Power Station (Milton Farm) | SPEN | Moffat | Storage | Accepted to connect | 49.84 |
| LAND AT LAMBRIGG FELL | ENWL | HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUP | Solar | Accepted to connect | 28 |
Grid supply points
Each grid supply point its sites are at, with the capacity of its own sites there.
| Grid supply point | DNO | Sites | Connected | Accepted to connect |
|---|---|---|---|---|
| Chapelcross | SPEN | 1 | – | 60 MW |
| Moffat | SPEN | 1 | – | 49.8 MW |
| HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUP | ENWL | 1 | – | 28 MW |
What changed recently
Changes to its sites found in both editions of each pair, newest first.
SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 2 sites matched. Every August site and every September site had a match in the other edition.
ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 1 site matched. Every September site and every October site had a match in the other edition.
- Erkeksi Power Station (Milton Farm)SPEN, May 2026 editionCustomer stated as Renewco Power Ltd (not stated in the April 2026 edition)
- Fechan Generation Facility (Minsca extension)SPEN, May 2026 editionCustomer stated as Renewco Power Ltd (not stated in the April 2026 edition)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?