Distribution / Sites / Customer

GREEN CAT RENEWABLES

Customer named in the DNOs’ registers

In SSEN’s November 2026 and SPEN’s September 2026 editions

The registers spell this customer’s name more than one way: “GREEN CAT RENEWABLES” (1 site), “GREEN CAT RENEWABLES LTD” (1 site), “Green Cat Renewables” (1 site) and “Green Cat Renewables Limited” (1 site).

4sites of 1 MW and over
65.8 MWcapacity
9.1 MWconnected (2 sites)
56.7 MWaccepted to connect (2 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
SSENNovember 2026 edition256.5 MW6.7 MW49.8 MW
SPENSeptember 2026 edition29.3 MW2.4 MW6.9 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Other or not stated149.8 MW–49.8 MW
Wind29.1 MW9.1 MW–
Solar16.9 MW–6.9 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
GREEN BURN WIND FARMSSENCOUPAR ANGUSOther or not statedAccepted to connect49.8
Balgonie Estate Solar FarmSPENRedhouseSolarAccepted to connect6.93
BINN FARM WIND FARMSSENABERNETHYWindConnected6.698
Rosehill Wind TurbinesSPENStirlingWindConnected2.4

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
COUPAR ANGUSSSEN1–49.8 MW
RedhouseSPEN1–6.9 MW
ABERNETHYSSEN16.7 MW–
StirlingSPEN12.4 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

SSEN, October 2026 edition to November 2026 edition, for this customer’s sites: 2 sites matched. Every October site and every November site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 2 sites matched. Every August site and every September site had a match in the other edition.

No change to any detail QueueWatch tracks for its sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?