QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / Sites / Customer

CLEATOR BATTERY STORAGE LIMITED

Customer named in the DNOs' registers

In ENWL's September 2026 edition

The registers spell this customer’s name more than one way: “CLEATOR BATTERY STORAGE LIMITED” (1 site) and “CLEATOR BATTERY STORAGE LTD” (1 site).

2sites of 1 MW and over
25 MWcapacity
10 MWconnected (1 sites)
15 MWaccepted to connect (1 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
ENWLSeptember 2026 edition225 MW10 MW15 MW

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage225 MW10 MW15 MW

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs' latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
CLEATOR BESSENWLHARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPStorageAccepted to connect15
WHINNEY HILL ROADENWLHARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPStorageConnected10

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPENWL210 MW15 MW

What changed recently

Changes to its sites found in both of two consecutive monthly editions of their DNO's register, the latest first.

ENWL, May 2026 edition to September 2026 edition, for this customer's sites: 2 sites matched. Every May site and every September site had a match in the other edition.

No change to the status, capacity, technology or customer of its sites in the editions QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose