Statera Energy Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Sundon Storage | Sundon 400kV Substation | Storage | 500 | 30 Oct 2027 | Gate 1 | Scoping |
Left the register since January 2021: St Dennis Hendra PV (49.9 MW), Loch Tarff Pumped Storage (300 MW), Beinn Pumped Hydro Storage (600 MW), Kintore Electrolysis (3 GW).
Recent changes
- Sundon StorageEngland and Wales, StorageMarked as Gate 1
- Sundon StorageEngland and Wales, StorageConnection date moved from 19 Dec 2031 to 30 Oct 2027 (−50 months)−50 mo
- Beinn Pumped Hydro StorageNorth Scotland, Hydro & marineLeft the register (600 MW from 31 Oct 2029)600 MW
- Sundon StorageEngland and Wales, StorageAdded to the registerNew
- Kintore ElectrolysisNorth Scotland, DemandLeft the register (3,000 MW from 31 Oct 2033)3,000 MW
- Kintore ElectrolysisNorth Scotland, DemandAdded to the registerNew
- Loch Tarff Pumped StorageNorth Scotland, Hydro & marineLeft the register (300 MW from 31 Oct 2029)300 MW
- Beinn Pumped Hydro StorageNorth Scotland, Hydro & marineAdded to the registerNew
- Loch Tarff Pumped StorageNorth Scotland, Hydro & marineAdded to the registerNew
- St Dennis Hendra PVEngland and Wales, SolarLeft the register (49.9 MW from 30 Jun 2025)49.9 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?