NORFOLK VANGUARD WEST LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Vanguard | Necton 400kV Substation | Offshore wind | 1,320 | 31 Dec 2027 +25 mo | Gate 2 | Consents Approved |
Recent changes
- VanguardEngland and Wales, Offshore windStage 2: Status changed from Scoping to Consents Approved
- VanguardEngland and Wales, Offshore windRestructured from 1 stage (1,320 MW from 1 Dec 2025) to 2 stages (400 MW from 31 Dec 2027, 920 MW from 1 Apr 2028). First connection date +25 months+25 mo
- VanguardEngland and Wales, Offshore windCustomer changed from NORFOLK VANGUARD LIMITED to NORFOLK VANGUARD WEST LIMITED
- VanguardEngland and Wales, Offshore windConnection point changed from Vanguard West Offshore Platform to Necton 400kV Substation
- VanguardEngland and Wales, Offshore windCapacity changed from 1,200 MW to 1,320 MW
- VanguardEngland and Wales, Offshore windConnection date moved from 1 Apr 2025 to 1 Dec 2025 (+8 months)+8 mo
- VanguardEngland and Wales, Offshore windConnection date moved from 4 Jan 2025 to 1 Apr 2025 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?