NORFOLK BOREAS LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Norfolk Boreas | Necton 400kV Substation | Offshore wind | 1,320 | 1 Oct 2029 | Not stated | Awaiting Consents |
Recent changes
- Norfolk BoreasEngland and Wales, Offshore windStage 2: Connection date moved from 31 Mar 2030 to 31 Dec 2030 (+9 months)+9 mo
- Norfolk BoreasEngland and Wales, Offshore windRestructured from 1 stage (1,320 MW from 1 Aug 2026) to 2 stages (400 MW from 1 Oct 2029, 920 MW from 31 Mar 2030). First connection date +38 months+38 mo
- Norfolk BoreasEngland and Wales, Offshore windConnection point changed from Norfolk Boreas Offshore Substation to Necton 400kV Substation
- Norfolk BoreasEngland and Wales, Offshore windRenamed from Boreas
- Norfolk BoreasEngland and Wales, Offshore windCapacity changed from 1,200 MW to 1,320 MW
- Norfolk BoreasEngland and Wales, Offshore windConnection date moved from 1 Apr 2027 to 1 Aug 2026 (−8 months)−8 mo
- Norfolk BoreasEngland and Wales, Offshore windConnection date moved from 4 Jan 2027 to 1 Apr 2027 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?