EQUINOR NEW ENERGY LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Equinor Celtic Sea 1 | Alverdiscott 400kV Substation | Offshore wind | 1,000 | 6 Dec 2036 | Gate 1 | Scoping |
| Equinor Celtic Sea 2 | EQUINOR 66KV OFFSHORE SUBSTATION | Offshore wind | 1,000 | 6 Dec 2036 | Not stated | Scoping |
| Whitson BESS NP | South Wales East Node A 275kV Substation | Storage | 350 | 30 Oct 2037 | Gate 1 | Scoping |
Left the register since January 2021: Equinor 3 (1.2 GW), Equinor 4 (1 GW), Equinor 5 (1 GW).
Recent changes
- Whitson BESS NPEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- Equinor Celtic Sea 2England and Wales, Offshore windGate marking removed (was Gate 1)
- Equinor Celtic Sea 2England and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to EQUINOR 66KV OFFSHORE SUBSTATION
- Equinor Celtic Sea 2England and Wales, Offshore windMarked as Gate 1
- Equinor Celtic Sea 1England and Wales, Offshore windMarked as Gate 1
- Whitson BESS NPEngland and Wales, StorageMarked as Gate 1
- Whitson BESS NPEngland and Wales, StorageCustomer changed from NORIKER POWER LTD to EQUINOR NEW ENERGY LIMITED
- Equinor Celtic Sea 1England and Wales, Offshore windTechnology changed from Storage, Offshore wind to Offshore wind
- Equinor Celtic Sea 2England and Wales, Offshore windTechnology changed from Storage, Offshore wind to Offshore wind
- Whitson BESS NPEngland and Wales, StorageConnection point changed from Whitson 275kV Substation to South Wales East Node A 275kV Substation
- Equinor Celtic Sea 1England and Wales, Offshore windTechnology changed from Offshore wind to Storage, Offshore wind
- Equinor Celtic Sea 2England and Wales, Offshore windTechnology changed from Offshore wind to Storage, Offshore wind
- Equinor Celtic Sea 1England and Wales, Offshore windTechnology changed from Storage, Offshore wind to Offshore wind
- Equinor Celtic Sea 2England and Wales, Offshore windTechnology changed from Storage, Offshore wind to Offshore wind
- Equinor Celtic Sea 1England and Wales, Offshore windTechnology changed from Demand, Storage, Offshore wind to Storage, Offshore wind
- Equinor Celtic Sea 2England and Wales, Offshore windTechnology changed from Demand, Storage, Offshore wind to Storage, Offshore wind
- Whitson BESS NPEngland and Wales, StorageAdded to the registerNew
- Equinor Celtic Sea 1England and Wales, Offshore windConnection point changed from Alverdiscott GSP to Alverdiscott 400kV Substation
- Equinor Celtic Sea 2England and Wales, Offshore windConnection point changed from Alverdiscott GSP to Alverdiscott 400kV Substation
- Equinor Celtic Sea 1England and Wales, Offshore windAdded to the registerNew
- Equinor Celtic Sea 2England and Wales, Offshore windAdded to the registerNew
- Equinor 3North Scotland, Offshore windLeft the register (1,200 MW from 31 Oct 2033)1,200 MW
- Equinor 4North Scotland, Offshore windLeft the register (1,000 MW from 31 Oct 2033)1,000 MW
- Equinor 5North Scotland, Offshore windLeft the register (1,000 MW from 31 Oct 2033)1,000 MW
- Equinor 3North Scotland, Offshore windAdded to the registerNew
- Equinor 4North Scotland, Offshore windAdded to the registerNew
- Equinor 5North Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?