EAST ANGLIA TWO LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| East Anglia Two | EA2A and EA2B 275/66kV Offshore Platform | Offshore wind | 880 | 31 Mar 2028 | Not stated | Awaiting Consents |
Recent changes
- East Anglia TwoEngland and Wales, Offshore windRestructured from 1 stage (860 MW from 31 Dec 2025) to 2 stages (860 MW from 31 Mar 2028, 20 MW from 31 Dec 2030). First connection date +27 months+27 mo
- East Anglia TwoEngland and Wales, Offshore windConnection date moved from 1 Nov 2024 to 31 Dec 2025 (+14 months)+14 mo
- East Anglia TwoEngland and Wales, Offshore windCustomer changed from SCOTTISHPOWER RENEWABLES (UK) LIMITED to EAST ANGLIA TWO LIMITED
- East Anglia TwoEngland and Wales, Offshore windRenamed from East Anglia 2
- East Anglia TwoEngland and Wales, Offshore windConnection date moved from 11 Jan 2024 to 1 Nov 2024 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?