CILFYNYDD NG LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Cilfynydd Green Energy Centre | Cilfynydd 400kV Substation | Storage with solar or wind | 1,025 | 30 Oct 2029 +12 mo | Gate 1 | Awaiting Consents |
Recent changes
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Connection date moved from 30 Oct 2028 to 30 Oct 2029 (+12 months)+12 mo
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from CILFYNYDD GREEN ENERGY LIMITED to CILFYNYDD NG LIMITED
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Demand, Storage, Solar to Demand, Storage, Solar, Onshore wind
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Demand, Storage, Solar to Demand, Storage, Solar, Onshore wind
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from CILFYNYDD NG LIMITED to CILFYNYDD GREEN ENERGY LIMITED
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Demand, Storage, Solar
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Demand, Storage, Solar
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windRenamed from CILFYNYDD NG LIMITED
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windRenamed from Cilfynydd Green Energy Centre
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from CILFYNYDD GREEN ENERGY LIMITED to CILFYNYDD NG LIMITED
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (1,025 MW from 30 Oct 2028) to 2 stages (400 MW from 30 Oct 2028, 625 MW from 31 Oct 2033)
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windCapacity changed from 400 MW to 1,025 MW
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Cilfynydd to Cilfynydd GSP)
- Cilfynydd Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose