Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Berwick Bank B Limited

Customer named in the TEC register

1project in the register
1.4 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Berwick Bank Offshore Wind Farm BBranxton 400kV SubstationOffshore wind1,38031 Oct 2029Not statedScoping

Left the register since January 2021: Firth of Forth Offshore Wind Farm 2A (1.2 GW), Firth of Forth Offshore Wind Farm 2B (1.2 GW).

Recent changes

  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windConnection point changed from Branxton 400/132KV Substation to Branxton 400kV Substation
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windConnection point changed from Berwick Bank B 275/66kV Offshore Substation to Branxton 400/132KV Substation
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Capacity changed from 250 MW to 1,150 MW
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Capacity changed from 900 MW to 230 MW
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 31 Oct 2029 to 30 Jun 2031 (+20 months)+20 mo
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 30 Oct 2029 to 31 Oct 2029 (1 day later)
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 1: Connection date moved from 27 Nov 2027 to 30 Oct 2029 (+23 months)+23 mo
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windStage 2: Connection date moved from 30 Dec 2027 to 30 Oct 2029 (+22 months)+22 mo
  • Firth of Forth Offshore Wind Farm 2ASouth Scotland, Offshore windLeft the register (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027)1,150 MW
  • Firth of Forth Offshore Wind Farm 2BSouth Scotland, Offshore windLeft the register (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027)1,150 MW
  • Berwick Bank Offshore Wind Farm BSouth Scotland, Offshore windAdded to the registerNew
  • Firth of Forth Offshore Wind Farm 2ASouth Scotland, Offshore windCustomer changed from SEAGREEN WIND ENERGY LIMITED to Berwick Bank B Limited
  • Firth of Forth Offshore Wind Farm 2BSouth Scotland, Offshore windCustomer changed from SEAGREEN WIND ENERGY LIMITED to Berwick Bank B Limited
  • Firth of Forth Offshore Wind Farm 2ASouth Scotland, Offshore windSubstation name updated in the register (from Branxton 400kV to Branxton 400kV Substation)
  • Firth of Forth Offshore Wind Farm 2BSouth Scotland, Offshore windSubstation name updated in the register (from Branxton 400kV to Branxton 400kV Substation)
  • Firth of Forth Offshore Wind Farm 2ASouth Scotland, Offshore windRestructured from 1 stage (700 MW from 1 Apr 2023) to 2 stages (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027). First connection date +44 months+44 mo
  • Firth of Forth Offshore Wind Farm 2BSouth Scotland, Offshore windRestructured from 1 stage (700 MW from 1 Apr 2024) to 2 stages (700 MW from 27 Nov 2026, 450 MW from 26 Nov 2027). First connection date +32 months+32 mo
  • Firth of Forth Offshore Wind Farm 2ASouth Scotland, Offshore windConnection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
  • Firth of Forth Offshore Wind Farm 2BSouth Scotland, Offshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO