BERWICK BANK A LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm A | Branxton 400kV Substation | Offshore wind | 1,380 | 31 Oct 2028 | Not stated | Scoping |
Recent changes
- Berwick Bank Offshore Wind Farm ASouth Scotland, Offshore windConnection point changed from Branxton 400/132KV Substation to Branxton 400kV Substation
- Berwick Bank Offshore Wind Farm ASouth Scotland, Offshore windRestructured from 1 stage (1,150 MW from 31 Oct 2028) to 2 stages (1,150 MW from 31 Oct 2028, 230 MW from 31 Oct 2029)
- Berwick Bank Offshore Wind Farm ASouth Scotland, Offshore windConnection date moved from 27 Nov 2027 to 31 Oct 2028 (+11 months)+11 mo
- Berwick Bank Offshore Wind Farm ASouth Scotland, Offshore windCustomer changed from Berwick Bank B Limited to Berwick Bank A Limited
- Berwick Bank Offshore Wind Farm ASouth Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?