Wylfa 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| BOOM Power Llanbabo Generation | Carrog Storage Facility Limited | Storage | 300 | 31 Oct 2028 | Not stated | Consents Approved |
Left the register since January 2021: New Project One (ONP01) (1.5 GW), Wylfa (0 MW).
Recent changes
- BOOM Power Llanbabo GenerationEngland and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
- BOOM Power Llanbabo GenerationEngland and Wales, StorageConnection date moved from 30 Oct 2026 to 31 Oct 2028 (+24 months)+24 mo
- BOOM Power Llanbabo GenerationEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- BOOM Power Llanbabo GenerationEngland and Wales, StorageConnection date moved from 30 Jun 2024 to 30 Oct 2026 (+28 months)+28 mo
- WylfaEngland and Wales, NuclearLeft the register (0 MW)0 MW
- BOOM Power Llanbabo GenerationEngland and Wales, StorageCustomer changed from BOOM POWER LTD to Carrog Storage Facility Limited
- BOOM Power Llanbabo GenerationEngland and Wales, StorageSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- WylfaEngland and Wales, NuclearSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
- BOOM Power Llanbabo GenerationEngland and Wales, StorageRestructured from 1 stage (300 MW from 30 Jun 2024) to 1 stage (300 MW from 30 Jun 2024)
- BOOM Power Llanbabo GenerationEngland and Wales, StorageAdded to the registerNew
- New Project One (ONP01)England and Wales, Offshore windLeft the register (1,500 MW from 1 Apr 2033)1,500 MW
- New Project One (ONP01)England and Wales, Offshore windConnection date moved from 4 Jan 2033 to 1 Apr 2033 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?