Weston Marsh 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| GT R4 Offshore Wind Farm | GT R4 LIMITED | Offshore wind | 1,500 | 30 Nov 2030 | Not stated | Scoping |
| Meridian Solar Farm | MERIDIAN SOLAR FARM LIMITED | Storage with solar or wind | 750 | 30 Jun 2033 | Gate 1 | Scoping |
| Spalding PV and BESS Station | ETP UK 1 LTD | Storage with solar or wind | 480 | 30 Jul 2033 | Not stated | Scoping |
Recent changes
- Meridian Solar FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windRenamed from GT R4 Wind Farm
- Meridian Solar FarmEngland and Wales, Storage with solar or windRenamed from Meridien Solar Farm
- Meridian Solar FarmEngland and Wales, Storage with solar or windCustomer changed from Downing Renewable Developments LLP to MERIDIAN SOLAR FARM LIMITED
- Meridian Solar FarmEngland and Wales, Storage with solar or windRenamed from Holbeach Marsh Energy Park
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from GREEN INVESTMENT GROUP LIMITED to GT R4 LIMITED
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from GIGL Offshore Substation to Weston Marsh 400kV Substation
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 1 Apr 2033 to 30 Nov 2030 (−28 months)−28 mo
- Meridian Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
- Spalding PV and BESS StationEngland and Wales, Storage with solar or windConnection point changed from Bicker Fen 400kV Substation to Weston Marsh 400kV Substation
- Spalding PV and BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windRenamed from GIGL Offshore Wind Farm
- GT R4 Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 4 Jan 2033 to 1 Apr 2033 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?