Thormanby 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Sedgeby Solar Farm | Sedgeby Solar Limited | Storage with solar or wind | 350 | 28 Oct 2033 | Gate 1 | Awaiting Consents |
| Poppleton PV & BESS Sub | YORK ENERGY PARK LIMITED | Storage with solar or wind | 250 | 24 Oct 2035 | Gate 1 | Scoping |
Recent changes
- Sedgeby Solar FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Poppleton PV & BESS SubEngland and Wales, Storage with solar or windMarked as Gate 1
- Sedgeby Solar FarmEngland and Wales, Storage with solar or windCustomer changed from BAYWA R.E. UK LIMITED to Sedgeby Solar Limited
- Sedgeby Solar FarmEngland and Wales, Storage with solar or windRenamed from Thormanby Solar PV & BESS
- Poppleton PV & BESS SubEngland and Wales, Storage with solar or windCustomer changed from O&G Solar (SPV 46) Limited to YORK ENERGY PARK LIMITED
- Poppleton PV & BESS SubEngland and Wales, Storage with solar or windConnection point changed from Poppleton 275kV Substation to Thormanby 400kV Substation
- Poppleton PV & BESS SubEngland and Wales, Storage with solar or windAdded to the registerNew
- Sedgeby Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?