Rye House 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|
Left the register since January 2021: Rye House (Tertiary) (57 MW).
Recent changes
- Rye House (Tertiary)England and Wales, StorageLeft the register (57 MW from 30 Jun 2027)57 MW
- Rye House (Tertiary)England and Wales, StorageConnection date moved from 30 Sep 2027 to 30 Jun 2027 (−3 months)−3 mo
- Rye House (Tertiary)England and Wales, StorageRestructured from 2 stages (49.9 MW from 31 Oct 2025, 7.1 MW from 31 Oct 2027) to 1 stage (57 MW from 30 Sep 2027). First connection date +23 months+23 mo
- Rye House (Tertiary)England and Wales, StorageCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS N LIMITED
- Rye House (Tertiary)England and Wales, StorageStage 1: Technology changed from Storage, Solar to Storage
- Rye House (Tertiary)England and Wales, StorageStage 2: Technology changed from Storage, Solar to Storage
- Rye House (Tertiary)England and Wales, StorageStage 1: Technology changed from Hybrid to Storage, Solar
- Rye House (Tertiary)England and Wales, StorageStage 2: Technology changed from Hybrid to Storage, Solar
- Rye House (Tertiary)England and Wales, StorageStage 1: Technology changed from Storage, Solar to Hybrid
- Rye House (Tertiary)England and Wales, StorageStage 2: Technology changed from Storage, Solar to Hybrid
- Rye House (Tertiary)England and Wales, StorageSubstation name updated in the register (from Rye House 400kV to Rye House 400kV Substation)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?