Nursling 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| EPL Hampshire | EPL NEWCO7 LIMITED | Storage with solar or wind | 480 | 31 Oct 2037 | Gate 1 | Scoping |
| NatPower Nursling Energy Park | SOUTHAMPTON ENERGY STORAGE LIMITED | Storage | 1,000 | 31 Oct 2037 | Not stated | Scoping |
| Nursling Flexible Generation | SOUTH ENG FLEXIBLE GENERATION LIMITED | Thermal (gas, biomass, waste) | 1,500 | 30 Oct 2038 | Not stated | Scoping |
| Nursling Tertiary | NURSLING ENERGY TWO LIMITED | Storage | 0 | Connected | Not stated | Built |
Recent changes
- NatPower Nursling Energy ParkEngland and Wales, StorageCustomer changed from NATPOWER MARINE GLOBAL LIMITED to SOUTHAMPTON ENERGY STORAGE LIMITED
- EPL HampshireEngland and Wales, Storage with solar or windMarked as Gate 1
- NatPower Nursling Energy ParkEngland and Wales, StorageCustomer changed from NATPOWER MARINE LIMITED to NATPOWER MARINE GLOBAL LIMITED
- Nursling Flexible GenerationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- EPL HampshireEngland and Wales, Storage with solar or windAdded to the registerNew
- NatPower Nursling Energy ParkEngland and Wales, StorageAdded to the registerNew
- Nursling TertiaryEngland and Wales, StorageSubstation name updated in the register (from Nursling 400kV to Nursling 400kV Substation)
- Nursling TertiaryEngland and Wales, Storage49.9 MW now connectedConnected
- Nursling TertiaryEngland and Wales, StorageStatus changed from Consents Approved to Built
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?