Northfleet East 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| NorthFleet Tertiary | CSE29 LIMITED | Storage with solar or wind | 49.9 | 30 Jun 2028 | Not stated | Scoping |
Left the register since January 2021: Hazells Farm (400 MW).
Recent changes
- NorthFleet TertiaryEngland and Wales, Storage with solar or windConnection point changed from NorthFleet 400kV Substation to Northfleet East 400kV Substation
- NorthFleet TertiaryEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2026 to 30 Jun 2028 (+24 months)+24 mo
- Hazells FarmEngland and Wales, StorageLeft the register (400 MW from 1 Sep 2030)400 MW
- Hazells FarmEngland and Wales, StorageCustomer changed from P3P PARTNERS LLP to Northfleet Devco Limited
- NorthFleet TertiaryEngland and Wales, Storage with solar or windConnection point changed from Northfleet East 400kV Substation to NorthFleet 400kV Substation
- NorthFleet TertiaryEngland and Wales, Storage with solar or windSubstation name updated in the register (from Northfleet East GSP to Northfleet East 400kV Substation)
- Hazells FarmEngland and Wales, StorageAdded to the registerNew
- NorthFleet TertiaryEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?