Northern Shetland 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| ARVEN OFFSHORE WIND FARM | ARVEN OFFSHORE WIND FARM LIMITED | Offshore wind | 1,800 | 31 Oct 2033 | Not stated | Scoping |
| Arven South Offshore Wind Farm | ARVEN SOUTH LIMITED | Offshore wind | 500 | 31 Oct 2033 | Not stated | Scoping |
| Sealtainn Offshore Wind Farm | Shetland Offshore Wind Limited | Offshore wind | 500 | 31 Oct 2033 | Not stated | Scoping |
Recent changes
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windConnection point changed from Blackhillock 400kV Substation to Northern Shetland 400kV Substation
- Arven South Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Kergord GSP to Northern Shetland 400kV Substation
- Sealtainn Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Sealtainn 275kV Offshore to Northern Shetland 400kV Substation
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windConnection point changed from Arven 400/66kV Offshore Substation to Blackhillock 400kV Substation
- Arven South Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Arven South 275kV Offshore Substation to Kergord GSP
- Arven South Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windConnection point changed from New Dounreay 400kV substation to Arven 400/66kV Offshore Substation
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windConnection point changed from ARVEN 400/66KV OFFSHORE SUBSTATION to New Dounreay 400kV substation
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windConnection point changed from New Dounreay 400kV substation to ARVEN 400/66KV OFFSHORE SUBSTATION
- ARVEN OFFSHORE WIND FARMNorth Scotland, Offshore windAdded to the registerNew
- Sealtainn Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?