High Marnham 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| JG Pears | JG PEARS GRID CONNECTION LIMITED | Multi-technology hub | 420 | 31 Oct 2033 +95 mo | Not stated | Built |
Left the register since January 2021: HIGH MARNHAM (240 MW).
Recent changes
- JG PearsEngland and Wales, Multi-technology hubCapacity changed from 0 MW to 420 MW
- JG PearsEngland and Wales, Multi-technology hubConnection date set to 31 Oct 2033
- JG PearsEngland and Wales, Multi-technology hubConnected MW moved between stages in the register (30 MW connected, unchanged)
- JG PearsEngland and Wales, Multi-technology hubStage removed (30 MW connected + 420 MW)
- JG PearsEngland and Wales, Multi-technology hubRestructured from 3 stages (17 MW connected, 420 MW from 31 Oct 2033, 13 MW connected) to 2 stages (0 MW, 30 MW connected + 420 MW)
- JG PearsEngland and Wales, Multi-technology hubStage 2: Connection date set to 30 Nov 2025
- JG PearsEngland and Wales, Multi-technology hubStage 2: Status changed from Built to Under Construction/Commissioning
- JG PearsEngland and Wales, Multi-technology hubStage 2: Connection date removed (was 30 Nov 2025)
- JG PearsEngland and Wales, Multi-technology hubStage 2: Status changed from Under Construction/Commissioning to Built
- JG PearsEngland and Wales, Multi-technology hubStage 2: 17 MW now connectedConnected
- JG PearsEngland and Wales, Multi-technology hubSubstation name updated in the register (from High Marnham GSP to High Marnham 275kV Substation)
- JG PearsEngland and Wales, Multi-technology hubStage 1: Technology changed from CHP, Solar to CHP, Storage, Solar, Onshore wind
- JG PearsEngland and Wales, Multi-technology hubStage 2: Connection date moved from 6 Sep 2019 to 30 Nov 2025 (+75 months)+75 mo
- JG PearsEngland and Wales, Multi-technology hubStage 2: Technology changed from CHP, Solar to CHP, Storage, Solar, Onshore wind
- JG PearsEngland and Wales, Multi-technology hubNew stage added (420 MW from 31 Oct 2033)
- HIGH MARNHAMEngland and Wales, Storage with solar or windLeft the register (240 MW from 1 Jun 2029)240 MW
- JG PearsEngland and Wales, Multi-technology hubStage 1: Technology changed from CHP to CHP, Solar
- JG PearsEngland and Wales, Multi-technology hubStage 2: Technology changed from CHP to CHP, Solar
- JG PearsEngland and Wales, Multi-technology hubSubstation name updated in the register (from High Marnham to High Marnham GSP)
- HIGH MARNHAMEngland and Wales, Storage with solar or windSubstation name updated in the register (from High Marnham to High Marnham GSP)
- HIGH MARNHAMEngland and Wales, Storage with solar or windAdded to the registerNew
- JG PearsEngland and Wales, Multi-technology hubStage 2: Connection date moved from 9 Jun 2019 to 6 Sep 2019 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?