South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Devol Moor Battery & Solar Project | Sunshine Project 03 Limited | Storage | 400 | 27 Sep 2027 −25 mo | Gate 1 | Scoping |
Recent changes
- Devol Moor Battery & Solar ProjectSouth Scotland, StorageConnection date moved from 17 Oct 2029 to 27 Sep 2027 (−25 months)−25 mo
- Devol Moor Battery & Solar ProjectSouth Scotland, StorageMarked as Gate 1
- Devol Moor Battery & Solar ProjectSouth Scotland, StorageCustomer changed from RELAY HOLDCO LIMITED to Sunshine Project 03 Limited
- Devol Moor Battery & Solar ProjectSouth Scotland, StorageConnection point changed from Devol Moor 400kV to Devol Moor 400/132kV
- Devol Moor Battery & Solar ProjectSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?