Corriemoillie 132/33kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Isenau Four | Isenau Energy Storage Resources Four Limited | Storage | 200 | 31 Oct 2033 | Not stated | Scoping |
| Corriemoillie Wind Farm | ROWAN ONSHORE WINDFARMS LIMITED | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Isenau FourNorth Scotland, StorageAdded to the registerNew
- Corriemoillie Wind FarmNorth Scotland, Onshore windCustomer changed from CORRIEMOILLIE WINDFARM LIMITED to ROWAN ONSHORE WINDFARMS LIMITED
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?