Coatbridge GSP
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| AGS Coatbridge | Advance Grid Solutions Limited | Storage | 60 | 30 Apr 2033 | Gate 1 | Scoping |
Left the register since January 2021: Scottish Water Airdrie STW 60MW BESS (45 MW).
Recent changes
- AGS CoatbridgeSouth Scotland, StorageMarked as Gate 1
- Scottish Water Airdrie STW 60MW BESSSouth Scotland, StorageLeft the register (45 MW from 31 Oct 2028)45 MW
- AGS CoatbridgeSouth Scotland, StorageAdded to the registerNew
- Scottish Water Airdrie STW 60MW BESSSouth Scotland, StorageConnection date moved from 31 Oct 2023 to 31 Oct 2028 (+60 months)+60 mo
- Scottish Water Airdrie STW 60MW BESSSouth Scotland, StorageSubstation name updated in the register (from Coatbridge 275/33kV GSP to Coatbridge GSP)
- Scottish Water Airdrie STW 60MW BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?