Clydesmill 275/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| AGS Calderside PV Solar | Advance Grid Solutions Limited | Solar | 63 | 31 May 2027 | Not stated | Scoping |
| Aitkenhead Farm BESS | Aitkenhead Storage Facility Limited | Storage | 300 | 30 Apr 2033 +54 mo | Gate 1 | Scoping |
Left the register since January 2021: Malcolmwood Farm BESS (60 MW).
Recent changes
- Aitkenhead Farm BESSSouth Scotland, StorageConnection date moved from 31 Oct 2028 to 30 Apr 2033 (+54 months)+54 mo
- Aitkenhead Farm BESSSouth Scotland, StorageMarked as Gate 1
- Malcolmwood Farm BESSSouth Scotland, StorageLeft the register (60 MW from 3 Jul 2026)60 MW
- Aitkenhead Farm BESSSouth Scotland, StorageCustomer changed from BOOM DEVELOPMENTS LTD to Aitkenhead Storage Facility Limited
- Aitkenhead Farm BESSSouth Scotland, StorageConnection point changed from Clyde's Mill 400kV Substation to Clydesmill 275/33kV
- Aitkenhead Farm BESSSouth Scotland, StorageTechnology changed from Storage to Demand, Storage
- Aitkenhead Farm BESSSouth Scotland, StorageConnection point changed from Easterhouse 132kV to Clyde's Mill 400kV Substation
- AGS Calderside PV SolarSouth Scotland, SolarConnection point changed from Westburn Road GSP to Clydesmill 275/33kV
- Malcolmwood Farm BESSSouth Scotland, StorageConnection point changed from Westburn Road GSP to Clydesmill 275/33kV
- AGS Calderside PV SolarSouth Scotland, SolarAdded to the registerNew
- Malcolmwood Farm BESSSouth Scotland, StorageAdded to the registerNew
- Aitkenhead Farm BESSSouth Scotland, StorageCapacity changed from 200 MW to 300 MW
- Aitkenhead Farm BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?