Beaw Field 132/33kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Beaw Field Wind Farm | BEAW FIELD SHETLAND LIMITED | Onshore wind | 102 | 29 Oct 2032 | Not stated | Consents Approved |
Recent changes
- Beaw Field Wind FarmNorth Scotland, Onshore windCapacity changed from 72 MW to 102 MW
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Nov 2028 to 29 Oct 2032 (+47 months)+47 mo
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2027 to 30 Nov 2028 (+20 months)+20 mo
- Beaw Field Wind FarmNorth Scotland, Onshore windCustomer changed from PEEL NRE WIND FARMS (YELL) LIMITED to BEAW FIELD SHETLAND LIMITED
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2026 to 1 Apr 2027 (+12 months)+12 mo
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection point changed from Yell to Beaw Field 132/33kV Substation
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2025 to 1 Apr 2026 (+12 months)+12 mo
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Beaw Field Wind FarmNorth Scotland, Onshore windCustomer changed from PEEL L&P WIND FARMS (YELL) LIMITED to Peel NRE Wind Farms (Yell) Limited
- Beaw Field Wind FarmNorth Scotland, Onshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?