Projects / England and Wales
Connection date
Connected
Gate
Not stated
Status
Built
Technology
Storage
Total capacity
49.9 MW
Connected now
49.9 MW
Still to connect
0 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-006810
Tracked since
18 Sep 2026

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

  • 21 Sep 2026 register
    Connection point changed from Iron Acton (South West) GSP to Warley GSP
  • 18 Sep 2026 register
    Added to the register

Also queued at Warley GSP

Substation view

No other projects in the register at this connection point.