Cambridgeshire Energy Storage Centre
Hydrostor UK Ltd at South Anglia Connection Node D 400kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Pumped storage + Thermal
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-006115
- In the register since
- June 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 7 Apr 2026 registerConnection point changed from Burwell South 400kV Substation to South Anglia Connection Node D 400kV Substation
- 27 Jun 2025 registerAdded to the register
Also at South Anglia Connection Node D 400kV Substation
Substation view1 other project, 1 GW still to connect at this substation in total. 500 MW is due to connect here before this project’s connection date of 31 Oct 2037.