Allt Domhain Wind Farm
ENERGYFARM ALLT DOMHAIN LTD at CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION
- Connection date
- 31 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Application submitted 31 Jul 2025
Scottish Government (S36), reference ECU00003231 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 64.8 MW
- Connected now
- 0 MW
- Still to connect
- 64.8 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-006015
- In the register since
- July 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Jun 2026 registerMarked as Gate 1
- 19 Jun 2026 registerConnection point changed from Carradale 1 GSP to CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION
- 29 Jul 2025 registerAdded to the register
Also at CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION
Substation view1 other project, 125 MW still to connect at this substation in total. 60 MW is due to connect here before this project’s connection date of 31 Oct 2035.