Melvich Wind Energy Hub (BEGA)
Melvich Wind Energy Hub Limited at Dounreay 2 275/33kV GSP Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage + Onshore wind
- Total capacity
- 43.2 MW
- Connected now
- 0 MW
- Still to connect
- 43.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-006005
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerMarked as Gate 1
- 30 Jun 2026 registerConnection point changed from Dounreay GSP to Dounreay 2 275/33kV GSP Substation
- 2 Jun 2026 registerStatus changed from Scoping to Awaiting Consents
- 27 Jun 2025 registerAdded to the register
Also at Dounreay 2 275/33kV GSP Substation
Substation viewNo other projects in the register at this connection point.