Vicarage Drove BESS Limited
- Connection date
- 30 Oct 2039
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 5 Feb 2025
Boston, reference B/24/0363 · Source: REPD - Technology
- Storage
- Total capacity
- 160 MW
- Connected now
- 0 MW
- Still to connect
- 160 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-006002
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerCustomer changed from AGR RENEWABLES LIMITED to VICARAGE DROVE BESS LIMITED
- 27 Jun 2025 registerAdded to the register
Also at Navenby 132kV Substation
Substation view2 other projects, 529 MW still to connect at this substation in total. 369 MW is due to connect here before this project’s connection date of 30 Oct 2039.