Projects / North Scotland
Meall Dearg
ENERGYFARM UK MEALL DEARG LTD at New North West 132kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-005981
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at New North West 132kV Substation
Substation view1 other project, 299 MW still to connect at this substation in total.