High Marnham 400MW Field BESS
Field High Marnham Ltd at Trent Valley South Connection Node G 400kV Substation
- Connection date
- 30 Oct 2039
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-005938
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 25 Aug 2026 registerMarked as Gate 1
- 29 Aug 2025 registerCustomer changed from Virmati Energy Ltd to Field High Marnham Ltd
- 29 Jul 2025 registerConnection point changed from High Marnham 400kV Substation to Trent Valley South Connection Node G 400kV Substation
- 27 Jun 2025 registerAdded to the register
Also at Trent Valley South Connection Node G 400kV Substation
Substation viewNo other projects in the register at this connection point.