Beinn Dearg
- Connection date
- 31 Oct 2037 +72 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 290 MW
- Connected now
- 0 MW
- Still to connect
- 290 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-005936
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2031 to 31 Oct 2037 (+72 months)
- 19 May 2026 registerConnection point changed from Beinn Dearg Hybrid Wind Farm to NEW TAYNUILT 132 KV SUBSTATION
- 19 May 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at NEW TAYNUILT 132 KV SUBSTATION
Substation viewNo other projects in the register at this connection point.