Edrom Green Energy Park
- Connection date
- 30 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-005818
- In the register since
- May 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Dec 2025 registerMarked as Gate 1
- 30 May 2025 registerAdded to the register
Also at Kelloe Mains 400kV Substation
Substation view2 other projects, 854 MW still to connect at this substation in total. 454 MW is due to connect here before this project’s connection date of 30 Oct 2033.