Patford Bridge BESS
Kona Energy Limited at Derbyshire Connection Node I 400kV Substation
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 228 MW
- Connected now
- 0 MW
- Still to connect
- 228 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-005065
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 Oct 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at Derbyshire Connection Node I 400kV Substation
Substation view3 other projects, 1.5 GW still to connect at this substation in total.
- Elmya Towcester BESSRPC ELMYA CARNATION TOWCESTER LIMITED, Storage, Gate 1Oct 2037550 MW
- Lightsource Patford BridgeLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2037240 MW
- Long Buckby Solar/BESSGreentech Invest UK (17) Limited, Storage with solar or wind, Gate 1Oct 2037500 MW