Astwood Solar Farm GEC
ASTWOOD GREEN ENERGY LTD at West Anglia Connection Node G 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 520 MW
- Connected now
- 0 MW
- Still to connect
- 520 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004799
- In the register since
- April 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 31 Oct 2037 to 31 Oct 2034 (−36 months)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2034 to 31 Oct 2037 (+36 months)
- 25 Aug 2026 registerMarked as Gate 1
- 7 Aug 2026 registerTechnology changed from Demand, Storage, Solar, Reactive compensation to Storage, Solar
- 29 Apr 2025 registerAdded to the register
Also at West Anglia Connection Node G 400kV Substation
Substation view2 other projects, 1.9 GW still to connect at this substation in total.