Braegrundie Farm
AEUK BATTERY PROJECT III LTD at Braegrundie Farm 132kV Substation
- Connection date
- 30 Jun 2030
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 95 MW
- Connected now
- 0 MW
- Still to connect
- 95 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004674
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Dec 2025 registerConnection point changed from Beauly GSP to Braegrundie Farm 132kV Substation
- 28 Nov 2025 registerMarked as Gate 1
- 28 Feb 2025 registerTransmission owner changed from SPT to SHET
- 27 Feb 2024 registerAdded to the register
Also at Braegrundie Farm 132kV Substation
Substation viewNo other projects in the register at this connection point.