Huntingdon High Impact Energy Hub 2
TELIS ENERGY UK LIMITED at West Anglia Connection Node H 400kVSubstation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Nuclear + Solar + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004508
- In the register since
- June 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Mar 2026 registerConnection point changed from Huntingdon 2 400kV Substation to West Anglia Connection Node H 400kVSubstation
- 13 Mar 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at West Anglia Connection Node H 400kVSubstation
Substation view1 other project, 2 GW still to connect at this substation in total.