- Connection date
- 31 Oct 2032
- Gate
- Not stated
- Status
- Scoping
- Technology
- Solar
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-004503
- In the register since
- March 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Jul 2026 registerCustomer changed from Renewable Energy Systems Limited to CAIRN DUHIE ENERGY LIMITED
- 30 Jun 2026 registerConnection point changed from Arbroath GSP to Arbroath 2 132/33kV GSP Substation
- 9 Dec 2025 registerCustomer changed from Cairn Duhie Energy Limited to Renewable Energy Systems Limited
- 29 Jul 2025 registerCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
- 28 Mar 2025 registerAdded to the register
Also at Arbroath 2 132/33kV GSP Substation
Substation viewNo other projects in the register at this connection point.