Chessington Estate
- Connection date
- 16 Nov 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-004420
- In the register since
- November 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Chessington 275kV Substation to Chessington 132kV
- 29 Jul 2025 registerCustomer changed from Bluestone Chessington 1 Ltd to Chessington BESS Ltd
- 27 Jun 2025 registerCustomer changed from Bluestone Energy Ltd to Bluestone Chessington 1 Ltd
- 28 Nov 2023 registerAdded to the register
Also at Chessington 132kV
Substation viewNo other projects in the register at this connection point.