Elmya Morningside BESS & PV
ELMYA RPC UK MORNINGSIDE LIMITED at Elmya Morningside 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004396
- In the register since
- October 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerAdded to the register
- 25 Aug 2026 registerLeft the register (400 MW from 31 Oct 2033)
- 27 Mar 2026 registerMarked as Gate 1
- 29 Oct 2024 registerAdded to the register
Also at Elmya Morningside 400kV Substation
Substation viewNo other projects in the register at this connection point.