- Connection date
- 31 Oct 2038
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 212 MW
- Connected now
- 0 MW
- Still to connect
- 212 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004388
- In the register since
- August 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerMarked as Gate 1
- 27 Aug 2024 registerAdded to the register
Also at North Kent Connection Node C 400kV Substation
Substation view1 other project, 532 MW still to connect at this substation in total. 320 MW is due to connect here before this project’s connection date of 31 Oct 2038.