Glenside Farm BESS
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 25 Feb 2025
Scottish Government (S36), reference ECU00005047 · Source: REPD - Technology
- Demand + Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004368
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Nov 2025 registerConnection date moved from 31 May 2028 to 31 Oct 2031 (+41 months)
- 27 Jun 2025 registerTechnology changed from Storage to Demand, Storage
- 27 Sep 2024 registerConnection point changed from Denny GSP to Denny North 275/132kV
- 31 Oct 2023 registerAdded to the register
Also at Denny North 275/132kV
Substation view1 other project, 600 MW still to connect at this substation in total. 200 MW is due to connect here before this project’s connection date of 31 Oct 2031.