West Common Ipers Lane
West Common BESS Limited at Solent Connection Node A 132kV Substation
- Connection date
- 30 Oct 2038
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-004352
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerMarked as Gate 1
- 10 Apr 2026 registerConnection point changed from Fawley GSP to Solent Connection Node A 132kV Substation
- 13 Jan 2026 registerCustomer changed from INNOVA RENEWABLES LIMITED to West Common BESS Limited
- 27 Jun 2025 registerAdded to the register
Also at Solent Connection Node A 132kV Substation
Substation viewNo other projects in the register at this connection point.