Transmission / Projects / England and Wales

Lower Frankton BESS

LOWER FRANKTON BESS LIMITED at Chirk 400kV Substation

Connection date
Left 27 Sep 2024
Gate
Not stated
Status
Scoping
Technology
Storage
Total capacity
500 MW
Connected now
0 MW
Still to connect
500 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-004349
In the register since
February 2024

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 27 Sep 2024 register
    Left the register (500 MW from 31 Oct 2036)
  • 27 Feb 2024 register
    Added to the register

Also at Chirk 400kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO