Patford Bridge PV & BESS
NORTHAMPTON ENERGY PARK LIMITED at Patford Bridge 400kV Substation
- Connection date
- 30 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004213
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Mar 2026 registerMarked as Gate 1
- 28 Jun 2024 registerCustomer changed from O&G Solar (SPV 54) Limited to NORTHAMPTON ENERGY PARK LIMITED
- 27 Feb 2024 registerCustomer changed from O&G Solar (SPV 39) Limited to O&G Solar (SPV 54) Limited
- 29 Sep 2023 registerAdded to the register
Also at Patford Bridge 400kV Substation
Substation view1 other project, 450 MW still to connect at this substation in total.